Updating a Task
- This interface is showing how to mark progress on an activity based on it’s percent of completion. This method is subjective and can lead to errors in projecting completion
- The Correct way is to specify an Actual Start date, a Remaining Duration and a Percent Complete. This allows the projection to stay up to date