BAD (EAC)

EAC = BAC / CPI

So if CPI = 0.5 and BAC was $10,000; we would have

EAC = 10,000 / 0.5 = 20,000

Or to re-phrase… If we are spending twice as much money based on current project status we can extrapolate that the whole project will cost twice as much

Remember when we had a CPI of 0.5 ?

We were Spending twice as fast as we should be