Math Fun with EAC

EAC = BAC / CPI

EAC = AC + ETC

EAC = AC + ((BACEV)/ CPI)

Or to re-phrase… The Estimate to Complete is the Actual Costs until this point added to the Estimated cost to finish the remainder of the Project

This is saying ETC = ((BAC-EV)/CPI) or If you subtract the current effort out of the plan you would have the remaining effort factor in the CPI and you can extrapolate what the remaining work will cost

You should know how to do the math magic, so you can extrapolate your projects completion