Cost & Schedule Variance
- CV = BCWP – ACWP
- The Amount the work completed was suppose to cost
- Minus
- The Amount the work completed actually did cost
- SV = BCWP – BCWS
- The Amount the work completed was suppose to cost
- Minus
- The Amount of the work that was to be completed by now
- Positive Number is good – Under Budget