1. What is the project estimate in calendar (elapsed) time?
( ) 12 months or less Low = 1 point
( ) 13 months to 24 months Medium = 2 points
( ) Over 24 months High = 3 points
2. What is the estimated number of person days for the system?
( ) 12 to 375 Low = 1 point
( ) 375 to 1875 Medium = 2 points
( ) 1875 to 3750 Medium = 3 points
( ) Over 3750 High = 4 points
3. Number of departments involved (excluding IT)
( ) One Low = 1 point
( ) Two Medium = 2 points
( ) Three or more High = 3 points
4. Is additional hardware required for the project?
( ) None Low = 0 points
( ) Central processor type change Low = 1 point
( ) Peripheral/storage device changes Low = 1
( ) Terminals Med = 2
( ) Change of platform, for example High = 3
PCs replacing mainframes
You may develop a
questionnaire to help
quantify the risk for your
project, like the one
partially shown here
You can only go so far in
quantifying risk because
you don’t know what you
don’t know